Marc Rawer
2013-07-16 17:02:41 UTC
Hi,
I'm running latest version of Agilo for trac on my site and see unexpeced
behavior on the story point burndown chart so I went online to your
demo-site and tested behavior there. I created 5 new userstories
(test{1..5}) and gave them increasing storypoints (1,2,3,5,8). I assigned
each of the user stories to a user and the srpint "story_point_test2". I
set the start date to tomorrow and committed the sprint. Result:
- the number of user stories was calculated correctely to total = 5
- the start of the burndown chart was marked at 19
- the ideal burndown line started at 8
=> seems like it does not take the sum for the ideal burndown but only the
last added story?
- I changed the story point of test5 to 0 and both start points drop to 0
- I changed the story points of test 4 to 20 and the start points went up
to 20
This looks like a bug to me because it only takes the last changed story
point value instead the complet sum of storypoints into account when
setting the start of the burndown chart.
Next, when a sprint is committed it seems that you can not change
responsibility anymore. Is this wanted this way?
Thanks in advance,
Marc
--
--
Follow Agilo on Twitter: http://twitter.com/agilofortrac
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-trac
http://freshmeat.net/projects/agiloforscrum
You have received this message because you are subscribed to
the "Agilo for Trac" Google Group. This group is focused on
supporting Agilo for Trac users and is moderated by
Agilo Software GmbH <http://www.agilosoftware.com>.
To post to this group, send email to agilo-/***@public.gmane.org
To unsubscribe from this group, send an email to
agilo+unsubscribe-/***@public.gmane.org
For more options, visit this group at
http://groups.google.com/group/agilo
---
You received this message because you are subscribed to the Google Groups "Agilo for Trac" group.
To unsubscribe from this group and stop receiving emails from it, send an email to agilo+unsubscribe-/JYPxA39Uh5TLH3MbocFF+G/***@public.gmane.org
For more options, visit https://groups.google.com/groups/opt_out.
I'm running latest version of Agilo for trac on my site and see unexpeced
behavior on the story point burndown chart so I went online to your
demo-site and tested behavior there. I created 5 new userstories
(test{1..5}) and gave them increasing storypoints (1,2,3,5,8). I assigned
each of the user stories to a user and the srpint "story_point_test2". I
set the start date to tomorrow and committed the sprint. Result:
- the number of user stories was calculated correctely to total = 5
- the start of the burndown chart was marked at 19
- the ideal burndown line started at 8
=> seems like it does not take the sum for the ideal burndown but only the
last added story?
- I changed the story point of test5 to 0 and both start points drop to 0
- I changed the story points of test 4 to 20 and the start points went up
to 20
This looks like a bug to me because it only takes the last changed story
point value instead the complet sum of storypoints into account when
setting the start of the burndown chart.
Next, when a sprint is committed it seems that you can not change
responsibility anymore. Is this wanted this way?
Thanks in advance,
Marc
--
--
Follow Agilo on Twitter: http://twitter.com/agilofortrac
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-trac
http://freshmeat.net/projects/agiloforscrum
You have received this message because you are subscribed to
the "Agilo for Trac" Google Group. This group is focused on
supporting Agilo for Trac users and is moderated by
Agilo Software GmbH <http://www.agilosoftware.com>.
To post to this group, send email to agilo-/***@public.gmane.org
To unsubscribe from this group, send an email to
agilo+unsubscribe-/***@public.gmane.org
For more options, visit this group at
http://groups.google.com/group/agilo
---
You received this message because you are subscribed to the Google Groups "Agilo for Trac" group.
To unsubscribe from this group and stop receiving emails from it, send an email to agilo+unsubscribe-/JYPxA39Uh5TLH3MbocFF+G/***@public.gmane.org
For more options, visit https://groups.google.com/groups/opt_out.