Hi there,

We have recently started using Agilo for Trac. First impressions are very
good but one seemingly obvious omission is that there is no milestone
burndown chart based on Story Points. I notice that there have been posts
about this back in 2009 when the response was that such a chart was planned
for an upcoming release. Does anybody know if this is still planned, and if
not, does anyone have a good work around?

Thanks

Andy
--
Follow Agilo on Twitter: http://twitter.com/agilofortrac
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-trac
http://freshmeat.net/projects/agiloforscrum

You have received this message because you are subscribed to
the "Agilo for Trac" Google Group. This group is focused on
supporting Agilo for Trac users and is moderated by
Agilo Software GmbH <http://www.agilosoftware.com>.

To post to this group, send email to agilo-/***@public.gmane.org
To unsubscribe from this group, send an email to
agilo+unsubscribe-/***@public.gmane.org
For more options, visit this group at
http://groups.google.com/group/agilo
Stefano Rago
2012-09-06 08:14:39 UTC
Permalink
Hi Andy,
We have recently started using Agilo for Trac. First impressions are very good but one seemingly obvious omission is that there is no milestone burndown chart based on Story Points. I notice that there have been posts about this back in 2009 when the response was that such a chart was planned for an upcoming release. Does anybody know if this is still planned, and if not, does anyone have a good work around?
Since Agilo 1.3.7, a sprint story point based burndown chart is available and we are still planning to implement release/milestone burndown charts.


Cheers


Stefano Rago
--
Follow Agilo on Twitter: http://twitter.com/agilofortrac
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-trac
http://freshmeat.net/projects/agiloforscrum

You have received this message because you are subscribed to
the "Agilo for Trac" Google Group. This group is focused on
supporting Agilo for Trac users and is moderated by
Agilo Software GmbH <http://www.agilosoftware.com>.

To post to this group, send email to agilo-/***@public.gmane.org
To unsubscribe from this group, send an email to
agilo+unsubscribe-/***@public.gmane.org
For more options, visit this group at
http://groups.google.com/group/agilo
Hywel Jones
2014-04-22 14:13:18 UTC
Permalink
Hi Stefano,

Just seen this from Sept 2012. Are there still plans to introduce burndown
charts for Releases/Milestones?

Regards,
Hywel
Post by Stefano Rago
Hi Andy,
We have recently started using Agilo for Trac. First impressions are very
good but one seemingly obvious omission is that there is no milestone
burndown chart based on Story Points. I notice that there have been posts
about this back in 2009 when the response was that such a chart was planned
for an upcoming release. Does anybody know if this is still planned, and if
not, does anyone have a good work around?
Since Agilo 1.3.7, a sprint story point based burndown chart is available
and we are still planning to implement release/milestone burndown charts.
Cheers
Stefano Rago
--
--
Follow Agilo on Twitter: http://twitter.com/agilofortrac
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-trac
http://freshmeat.net/projects/agiloforscrum

You have received this message because you are subscribed to
the "Agilo for Trac" Google Group. This group is focused on
supporting Agilo for Trac users and is moderated by
Agilo Software GmbH <http://www.agilosoftware.com>.

To post to this group, send email to agilo-/***@public.gmane.org
To unsubscribe from this group, send an email to
agilo+unsubscribe-/***@public.gmane.org
For more options, visit this group at
http://groups.google.com/group/agilo

---
You received this message because you are subscribed to the Google Groups "Agilo for Trac" group.
To unsubscribe from this group and stop receiving emails from it, send an email to agilo+unsubscribe-/JYPxA39Uh5TLH3MbocFF+G/***@public.gmane.org
For more options, visit https://groups.google.com/d/optout.
Stefano Rago
2014-04-28 08:35:58 UTC
Permalink
Hi there,
Just seen this from Sept 2012. Are there still plans to introduce burndown charts for Releases/Milestones?
Yes this is still in the plans, although it's not in our top priorities at the moment unfortunately.

If you are interested, this is what we will be focusing on in the near future:

- Upgrade to internal continuous integration and testing infrastructure
- Improvement of the UI
- Improvement of the overall quality and stability and usability of the tool
- More flexibility for the whiteboard, allowing users to show more than only stories and tasks

Cheers,

Stefano Rago
--
--
Follow Agilo on Twitter: http://twitter.com/agilofortrac
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-trac
http://freshmeat.net/projects/agiloforscrum

You have received this message because you are subscribed to
the "Agilo for Trac" Google Group. This group is focused on
supporting Agilo for Trac users and is moderated by
Agilo Software GmbH <http://www.agilosoftware.com>.

To post to this group, send email to agilo-/***@public.gmane.org
To unsubscribe from this group, send an email to
agilo+unsubscribe-/***@public.gmane.org
For more options, visit this group at
http://groups.google.com/group/agilo

---
You received this message because you are subscribed to the Google Groups "Agilo for Trac" group.
To unsubscribe from this group and stop receiving emails from it, send an email to agilo+unsubscribe-/JYPxA39Uh5TLH3MbocFF+G/***@public.gmane.org
For more options, visit https://groups.google.com/d/optout.
Loading...