Discussion:
[Agilo for Trac] Converting a task to a User story messes up the burndown chart
Per
2013-12-18 15:26:47 UTC
Permalink
Hi,

sometimes we want to remove a task from a sprint and convert it to a User
story and put it back on the product backlog.

However we have noticed that the remaining hours of the original task will
still be counted in the burndown chart but not in the sprint backlog view.

To reproduce:
Convert a task to a User story and remove the sprint. Also remove any link
to referenced User stories.
The burndown will still include the tasks remaining time.

Versions:
Trac 1.0.1
Agilo 1.3.12 Pro

Regards
Per
--
--
Follow Agilo on Twitter: http://twitter.com/agilofortrac
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-trac
http://freshmeat.net/projects/agiloforscrum

You have received this message because you are subscribed to
the "Agilo for Trac" Google Group. This group is focused on
supporting Agilo for Trac users and is moderated by
Agilo Software GmbH <http://www.agilosoftware.com>.

To post to this group, send email to agilo-/***@public.gmane.org
To unsubscribe from this group, send an email to
agilo+unsubscribe-/***@public.gmane.org
For more options, visit this group at
http://groups.google.com/group/agilo

---
You received this message because you are subscribed to the Google Groups "Agilo for Trac" group.
To unsubscribe from this group and stop receiving emails from it, send an email to agilo+unsubscribe-/JYPxA39Uh5TLH3MbocFF+G/***@public.gmane.org
For more options, visit https://groups.google.com/groups/opt_out.
Stefano Rago
2014-01-06 08:11:44 UTC
Permalink
Hi Per,
sometimes we want to remove a task from a sprint and convert it to a User story and put it back on the product backlog.
However we have noticed that the remaining hours of the original task will still be counted in the burndown chart but not in the sprint backlog view.
Convert a task to a User story and remove the sprint. Also remove any link to referenced User stories.
The burndown will still include the tasks remaining time.
Trac 1.0.1
Agilo 1.3.12 Pro
Thanks a lot for reporting this problem and the details to reproduce it. I have filed a bug in our tracking system and it will be addressed as soon as possible.

Cheers


Stefano Rago
--
--
Follow Agilo on Twitter: http://twitter.com/agilofortrac
Please support us by reviewing and voting on:
http://userstories.com/products/8-agilo-for-scrum
http://ohloh.net/p/agilo-trac
http://freshmeat.net/projects/agiloforscrum

You have received this message because you are subscribed to
the "Agilo for Trac" Google Group. This group is focused on
supporting Agilo for Trac users and is moderated by
Agilo Software GmbH <http://www.agilosoftware.com>.

To post to this group, send email to agilo-/***@public.gmane.org
To unsubscribe from this group, send an email to
agilo+unsubscribe-/***@public.gmane.org
For more options, visit this group at
http://groups.google.com/group/agilo

---
You received this message because you are subscribed to the Google Groups "Agilo for Trac" group.
To unsubscribe from this group and stop receiving emails from it, send an email to agilo+unsubscribe-/JYPxA39Uh5TLH3MbocFF+G/***@public.gmane.org
For more options, visit https://groups.google.com/groups/opt_out.
Loading...